WATER & SEWER

Whether it is the collection and distribution system or a state of the art treatment facility, our experienced staff can meet the challenge. Dean’s understand that design and build changes are inevitable in underground construction, it is our goal to keep every project moving with minimal delays. 


Sand Lake Waste Water Treatment Facility  
Owner: Village of Sand Lake
General Contractor: Dean’s Excavating
Subcontractors: Grand Tech Inc, Farm Services and Ark’s Electric.
Engineer: Fleis & Vandenbrink
Year Completed: 2013
Highlights: Work included sanitary sewer reconstruction, new lift station, sludge removal from existing lagoons, reconstruction of existing ponds, irrigation pump station, and irrigation system. 


Mill Creek and York Creek Sewer
Owner: North Kent Sewer Authority
General Contractor: Dean's Excavating
Engineer: Prein and Newhoff
Year Completed: 2011, 2012
Highlights: York Creek Sewer – Work included reconstruction of 2,900 feet of sanitary sewer, lining of 1,000 feet of sanitary sewer between Bristol Ave and Cordes Avenue in Alpine township.
Mill Creek – Work included reconstruction of 1,000 feet of 12 inch – 21 inch sanitary sewer in Lamoureux Drive. Rehabilitation of existing manholes and lining of 2,100 feet of 18 inch sanitary sewer.